NBRB STOPS ILLEGAL BUILDING SITES IN HOIMA CITY

Friday our Compliance, Enforcement & Legal Teams last week responded to calls by the leadership of Hoima City, following public complaints about building operations failing to meet the building and safety standards.

The first building on One Street lacked a building permit and was being constructed using the prohibited Steel and Timber Composite Building Method. The team inspected the building and condoned it off.

The second building under renovation on Old Tooro/Byabachwezi Road had outlived its lifespan and failed the Structural integrity test performed on its structural elements. It did not also fulfil the complete requirements for approval.

Renovation was stopped immediately and the site condoned off by NBRB’s enforcement team.